ICB LOWER OVAL
Client
Principal Contractor
PROJECT VALUE
$2.2M
LOCATION
Pavely Civil Engineering was responsible for producing the complete cost estimate for the redevelopment of the lower oval at Islamic College Brisbane (ICB). This contributed to a successful competitive tender award, with the project now in the delivery phase.
The ICB lower oval project involves redevelopment of a greenfield site, including tree clearing, bulk earthworks, retaining walls, stormwater drainage, irrigation and landscaping. The site presents access constraints for heavy plant and equipment, rock excavation requirements and specialist Terramesh retaining wall construction.
Preconstruction Deliverables:
BOQ creation and quantity take-offs
Full f irst-principles cost estimate
Work package creation and quote requests
Assumptions and exclusions register
Construction program
Tender addendum updates
Construction Phase Deliverables:
Supplier engagement and feasibility assessment of replacing the Terramesh retaining wall with a boulder wall to improve serviceability.
Health, safety and quality documentation, including construction management plans, erosion and sediment control coordination and safe work method statements.
End-to-end procurement of surveying, tree clearing, pipe supply, retaining walls and material export locations.
Ongoing technical support for delivery teams including RFIs for changing RCP pipes to plastic pipes to reduce lead times.
Variations and progress claim support.
Attending regular site visits to track progress and inform pricing assumptions for future tenders.
SOUTH BRISBANE, AUSTRALIA
completion date
April 2027